Lessons Learned

Lesson Learned





No user selected

Report No.

273

Discipline/Origin

Drilling
No origin

Well

Rungne
30/6-30

Date created

2019/09/30
2259 days ago

Project Phase

Operational
Project Phase

LL Type/Classification

Planning
Negative

Transocean Arctic


What happened in Intermediate section:
The 5 1/2″ DP handling pup made up to the 9 5/8″ casing hanger running tool was too short. The length was 3.89 m. With this length, the shear ram will cut into the tooljoint of first 5 1/2″ DP single made up this pup.

What Was Planned

Running 9 5/8″ casing

What Was Learned

This means that the shear ram can’t be used during the cementing operation. No issue if the 5 1/2″ handling pup had been 0.5 m longer.

What Actions Are Required

DQ to look at the BOP spaceout drawing when planning & providing handling pup to the RT for future wells.